Spring 2022 |
Gedling Access Road opens to traffic midday on 22 March |
January 2020 |
Proposed start of main construction works |
November 2019 |
Pre-site clearance planning conditions discharged |
October 2019 |
Completion of Glebe Farm demolition |
September 2019 |
Notice given that the Secretary of State has given a certificate under section 19 in respect of exchange land |
August 2019 |
Phase 2 drainage works commence |
July 2019 |
Notice given that the Secretary of State intends to give a certificate under section 19 in respect of exchange land |
June 2019 |
Public Inquiry (all outstanding objections withdrawn in advance and Inquiry did not open) |
April 2019 |
Ecology mitigation works at Glebe Farm |
November / December 2018 |
Notification and Publicity of the CPO and SRO. Objection period closed 21 December 2018. |
October 2018 |
CPO and SRO made on 25 October 2018 |
March 2018 |
Additional ground investigation undertaken along the route of Gedling Access Road |
December 2017 |
Pre-commencement planning conditions discharged |
|
Commencement of advanced drainage works - phase 1 |
|
Lawful commencement of development confirmed |
November 2017 |
Diversion of utilities (electricity) on Arnold Lane |
March 2017 |
Nottinghamshire County Council approve making of the CPO |
July 2016 |
Letters sent out to land owners informing them of the CPO process |
April 2016 |
Borehole drilling for ground investigation |
January 2016 |
Diversion of utilities (gas) on Arnold Lane |
December 2014 |
Planning permission granted by Gedling Borough Council for the Gedling Access Road |