Shale gas sites in Nottinghamshire

Exploratory tests for shale gas have been undertaken at two sites in Nottinghamshire.

Tinker Lane, near Barnby Moor and Blyth

Drilling at the exploratory shale gas site off the A634 between Barnby Moor and Blyth (Planning Permission Ref: 1/16/00773/CDM) was completed in January 2019.  All drilling equipment was removed from the site with the exception of the well pad and the site entered into an evaluation phase.

IGas subsequently released operational updates that confirmed that a shale interval was encountered before penetrating the key Dinantian limestone geophysical marker, but the shales encountered did not include the primary target, the Bowland shale.

Subsequent to this, IGas confirmed that the well would be plugged and abandoned and the site restored back to its original agricultural use.  Restoration works were undertaken during the summer of 2019 and, in October 2019, the County Council formally confirmed that restoration works had been completed to its satisfaction and in accordance with the planning permission.  The site is now in a five year aftercare period and officers will continue to monitor the site during this period to check the condition of the arable land and the perimeter planting that was also undertaken.

In light of the above, the final Community Liaison Group meeting was held on 25 September 2019.

Misson Springs, land off Springs Road

Planning permission was granted in May 2017 (Planning Permission Ref: 1/15/01498/CDM) for the development of a hydrocarbon wellsite and drilling of up to two exploratory hydrocarbon wells (one vertically and the other horizontally) on land off Springs Road, Misson.​

Following the drilling of the vertical well, IGas announced on 11 March that the drilling had encountered a hydrocarbon bearing shale sequence of over 250 metres, including the upper and lower Bowland shale. IGas report that significant gas indications were observed throughout the shale section and additionally within sands in the Millstone Grit sequence. The drill rig has been removed from the site and the horizontal well remains to be drilled. IGas has subsequently confirmed that operations have now moved into the Phase 3 (evaluation) phase.

Share this page?