Minerals and Waste Development Framework Minerals and Waste Development Scheme
The Minerals and Waste Development Scheme sets out the timetable for preparing the new documents which will make up the Nottinghamshire Minerals and Waste Development Framework. It looks ahead 3 years with indicative dates for plans which will not be completed until later. The current scheme came into effect on 21 June 2007 and can be viewed below.
The Minerals and Waste Development Scheme 2007 [PDF 748KB]
Current progress in document preparation ( last updated December 2009)
The 2007 scheme is completely out of date in terms of the timetable. An indicative timetable of actual progress and expected adoption dates for the Minerals and Waste Core Strategy is set out below. Development control policy and site allocation documents are to follow which will not be submitted until the relevant Core Strategy has been found ‘sound’ at the examination stage. A revised timetable for these documents has yet to be prepared.
Key Milestone | Joint Waste Core Strategy | Minerals Core Strategy |
Informal Consultation | ||
| Issues and options | October 2006 | April 2010 |
| Revised issues and options | February 2010 | n/a |
| Preferred options | September 2010 | November 2010 |
Submission and examination | ||
| Pre-submission - formal Representation period | April 2011 | June 2011 |
| Submission to Secretary of State - examination begins. | September 2011 | October 2011 |
| Pre-hearing meeting | November 2011 | January 2012 |
| Hearing stage | December 2011 | February 2012 |
Adoption | ||
| Receipt of Inspector's Report leading to : | March 1012 | May 2012 |
| Adoption if document found sound or | July 2012 | September 2012 |
| document withdrawn if not found sound | July 2012 | September 2012 |
Above dates indicative and subject to change.
The timing and need for a new scheme will be considered in the next Annual Monitoring Report which will be submitted to Government by 31 December 2009. A proposed new scheme was submitted to Government in April 2009 but following further advice from the Government and the Planning Inspectorate this scheme was later withdrawn.
Previous schemes including the withdrawn scheme can be viewed on Development Framework Archive page.
Current progress on document preparation is summarised below:
Waste Core Strategy -General public consultation on issues and options took place in late 2006. Since then further evidence gathering has been carried focusing on potential sites for new waste management facilities. Revised Issues and Options consultation is planned to commence in January 2010.
Minerals Core Strategy and Safeguarding Document - Evidence gathering is now underway and it is planned to commence general public consultation on issues and options in April 2010. Informal consultation with key stakeholders on a draft minerals safeguarding background paper took place in April 2009.
Monitoring the Minerals and Waste Development Scheme
As noted above the scheme is subject to annual monitoring via the Annual Monitoring Report which has to be submitted to Government by the end of each calendar year. If a new scheme is proposed in response to the findings of the Annual Monitoring Report this must be submitted to Government for approval before it can come into effect.
Updates will appear here.
Adopted Plans
For a list of Adopted Plans, and other completed documents that form part of the development framework see Adopted Plans and Development Documents.
Plug-ins and viewers
In order to read the documents linked from this page you will need Word (for doc
format) or Adobe Acrobat reader (for pdf
format). You can download these free of charge by going to plug-ins and viewers
Useful information on pdf files and their accessibility is available at: http://access.adobe.com