Application no:ES/1144
Site reference:3711/W
Location:Land at Former Rufford Colliery, Rainworth
Proposal:Construction and operation of an Energy Recovery Facility through the incineration of waste together with ancillary infrastructure, including a waste bulking/transfer station, administration/visitor centre, landscaping and creation of new internal haul road.
Date received:30/11/2007
Valid date:03/12/2007
Start of Public Consultation:03/12/2007
Case Officer:Mike Hankin
Case Officer telephone:0115 9774320
Contact e-mail: development.planning@nottscc.gov.uk
Agent's name:RPS Planning & Development
Agent's address:Conrad House
Beaufort Square
Chepstow
Monmouthshire
Applicant's name:Veolia Environmental Services Nottinghamshire
Applicant's address:Trentside Offices
Freeth Street
Nottingham

Planning Submission Documents

Planning Application Submission – contained on cd rom.  This is split into a Non-technical summary, a planning supporting statement, the Environmental Impact Assessment and the supporting technical appendixes.

ATTENTION:

Some files particularly those containing complex drawings have been reduced in file size and print quality to assist in download speeds.  The original full size documents are available in the planning application CD-ROM. Copies are available upon request by contacting the Development Control Team.

ES Non-Technical Summary

Figure 1.1 Site Location Plan [PDF 815KB]pdf logo

Figure 1.2 Application Boundary [PDF 181KB]pdf logo

Figure 2.5 Site Context plan [PDF 750KB]pdf logo

Figure 4.1 ERF Input Output Flow Diagram [PDF 93KB]pdf logo

Figure 4.2 process flow diagram [PDF 3010KB]pdf logo

Figure 4.3 Landscape Masterplan [PDF 3080KB]pdf logo

Figure 4.9 Computer Generated 3D Image of proposed ERF [PDF 395KB]pdf logo

Figure 9.1A Designations within 2km [PDF 1300KB]pdf logo

Non-Technical Summary text [PDF 250KB]pdf logo

Volume 1 - Environmental Statement

Chapter 1 Introduction [PDF 371KB]pdf logo

Chapter 2 The Site and its Setting {PDF 163KB]pdf logo

Chapter 3 Planning History and Policy [PDF 751KB]pdf logo

Chapter 4 Development Proposals [PDF 720KB]pdf logo

Chapter 5 Need and Alternatives [PDF 714KB]pdf logo

Chapter 6 Traffic and Transport [PDF 388KB]pdf logo

Chapter 7 Air Quality [PDF 961KB]pdf logo

Chapter 8 Landscape and Visual [PDF 923KB]pdf logo

Chapter 9 Ecology [PDF 551KB]pdf logo

Chapter 10 Hydrology and Flood [PDF 352KB]pdf logo

Chapter 11 Grounf Conditions and Hydrogeology [PDF 388KB]pdf logo

Chapter 12 Noise [PDF 750KB]pdf logo

Chapter 13 Waste [PDF 298KB]pdf logo

Chapter 14 Socio Economic Impacts [PDF 334KB]pdf logo

Chapter 15 Archaeology and Cultural Heritage [PDF 310KB]pdf logo

Chapter 16 Land Use [PDF 268KB]pdf logo

Chapter 17 Summary [PDF 661KB]pdf logo

Glossary of Terms [PDF 247KB]pdf logo

Volume 1 - Environmental Statement - Figures

Figure 1.1 Site Location Plan [PDF 812KB]pdf logo

Figure 1.2 Application Boundary [PDF 179KB]pdf logo

Figure 2.1 Existing Site Layout - Topographical Survey [PDF 1467KB]pdf logo

Figure 2.2 Aerial Photograph 1 [PDF 449KB]pdf logo

Figure 2.3 Aerial Photograph 2 [PDF 459KB]pdf logo

Figure 2.4 Pit Head Area and Associated Development [PDF 2279KB]pdf logo

Figure 2.5 Site Context plan [PDF 748KB]pdf logo

Figure 2.6 Public Rights of Way and Open Access [PDF 800KB]pdf logo

Figure 4.1 ERF Input Output Flow Diagram [PDF 93KB]pdf logo

Figure 4.2 process flow diagram [PDF 2997KB]pdf logo

Figure 4.3 Landscape Masterplan [PDF 418KB]pdf logo

Figure 4.4 Surface Water Management Strategy [PDF 1804KB]pdf logo

Figure 4.5 Site Plan Showing ERF Layout [PDF 1737KB]pdf logo

Figure 4.6 West and East Facades [PDF 340KB]pdf logo

Figure 4.7 North and South Facades [PDF 315KB]pdf logo

Figure 4.8 Long Section A-A [PDF 626KB]pdf logo

Figure 4.9 Computer Generated 3D Image of proposed ERF [PDF 393KB]pdf logo

Figure 4.10 Administration Building Elevations [PDF 192KB]pdf logo

Figure 4.11 Transformer Building [PDF 191KB]pdf logo

Figure 4.12 Vehicle Circulation Plan [PDF 474KB]pdf logo

Figure 4.13 Pedestrian Visitors Route [PDF 424KB]pdf logo

Figure 4.14 General Arrangement of New Internal Colliery Road [PDF 190KB]pdf logo

Figure 4.15 Cross Section of New Internal Colliery Road [PDF 133KB]pdf logo

Figure 4.16 Construction Phase Site Facilities [PDF 1376KB]pdf logo

Figure 5.1 Forecast Municipal Solid Waste Generation [PDF 719KB]pdf logo

Figure 5.2 Forecast Recycling of Municipal Waste Arisings [PDF 764KB]pdf logo

Figure 5.3 Management of Residual Waste [PDF 109KB]pdf logo

Figure 5.4 Performance against LDA with ERF [PDF 211KB]pdf logo

Figure 5.5 Performance against LDA with Do Nothing [PDF 129KB]pdf logo

Figure 5.6 Design Evolution [PDF 526KB]pdf logo

Figure 6.1 Site Location Plan [PDF 1144KB]pdf logo

Figure 6.2 Site and Local Transport Network [PDF 465KB]pdf logo

Figure 7.1 ERF Site and Nearest Sensitive Receptors [PDF 1505KB]pdf logo

Figure 7.2 Contour Plot Predicted annual n02 [PDF 779KB]pdf logo

Figure 7.3 Contour Plot Predicted annual pm10 [PDF 823KB]pdf logo

Figure 8.1 Existing Site Context [PDF 577KB]pdf logo

Figure 8.2 Topographical Context [PDF 963KB]pdf logo

Figure 8.3 Landscape Policy Context [PDF 631KB]pdf logo

Figure 8.4 Landscape Character Context [PDF 678KB]pdf logo

Figure 8.5 75m Chimney ZVI [PDF 736KB]pdf logo

Figure 8.6 40m Roof ZVI [PDF 790KB]pdf logo

Figure 8.7 Viewpoint Locations [PDF 592KB]pdf logo

Figure 8.8 Viewpoint 1 Assessment [PDF 361KB]pdf logo

Figure 8.8b Viewpoint 1 Photomontage [PDF 1713KB]pdf logo

Figure 8.9 Viewpoint 2 Assessment [PDF 2594KB]pdf logo

Figure 8.9b Viewpoint 2 Photomontage [PDF 754KB]pdf logo

Figure 8.10 Viewpoint 3 [PDF 2832KB]pdf logo

Figure 8.11 Viewpoint 4 [PDF 2664KB]pdf logo

Figure 8.11b Viewpoint 4 Photomontage [PDF 3005KB]pdf logo

Figure 8.12 Viewpoint 5 [PDF 3133KB]pdf logo

Figure 8.13 Viewpoint 6 [PDF 2487KB]pdf logo

Figure 8.13b Viewpoint 6 Photomontage [PDF 2884KB]pdf logo

Figure 8.14 Viewpoint 7 [PDF 2564KB]pdf logo

Figure 8.15 Viewpoint 8 [PDF 869KB]pdf logo

Figure 8.16 Viewpoint 9 [PDF 1386KB]pdf logo

Figure 8.17 Viewpoint 10 [PDF 3150KB]pdf logo

Figure 8.17b Viewpoint 10 Photomontage [PDF 3390KB]pdf logo

Figure 8.18 Viewpoint 11 [PDF 865KB]pdf logo

Figure 8.19 Viewpoint 12 [PDF 1133KB]pdf logo

Figure 8.20 Viewpoint 13 [PDF 447KB]pdf logo

Figure 9.1 Ecological Constraints Map [PDF 954KB]pdf logo

Figure 9.14 Dingy Skipper Survey Transect [PDF 1383KB]pdf logo

Figure 9.1A Designations within 2km [PDF 431KB]pdf logo

Figure 9.1B Designations within 10km [PDF 354KB]pdf logo

Figure 9.2 Phase 1 Main Map Main Site [PDF 2236KB]pdf logo

Figure 9.3 Phase 1 Map Access Road [PDF 254KB]pdf logo

Figure 9.4 Location of Reptile Refugia [PDF 264KB]pdf logo

Figure 9.5 Breeding Bired Survey Transect [PDF 251KB]pdf logo

Figure 10.1 Surface Water Features [PDF 1467KB]pdf logo

Figure 10.2 Environment Agency Flood Map [PDF 449KB]pdf logo

Figure 11.1 Proposed Site Layout and Sample locations [PDF 337KB]pdf logo

Figure 11.2 Solid and Drift Geology [PDF 1220KB]pdf logo

Figure 11.3 potential Groundwater receptor plan-high [PDF 919KB]pdf logo

Figure 12.1 Noise Monitoring Locations [PDF 652KB]pdf logo

Figure 12.2 - Grid Noise - All Sources (Internal, External, Glass Bays & HGV) [PDF 499KB]pdf logo

Figure 12.3 Traffic Noise Assessment - Grid Noise Map - 2011 Base Flows (Incl Committed Dvpt) [PDF 596KB]pdf logo

Figure 12.4 Traffic Noise Assessment - Grid Noise Map - 2011 Base + Dvpt Flows [PDF 589KB]pdf logo

Figure 12.5 Traffic Noise Assessment - Grid Noise Map - 2026 Base Flows (Incl Committed Dvpt) [PDF 573KB]pdf logo

Figure 12.6 Traffic Noise Assessment - Grid Noise Map - 2026 Base + Development Flows [PDF 596KB]pdf logo

Figure 12.7 Traffic Noise Assessment - Facade Noise Map - 2011 Increase due to Development [PDF 562KB]pdf logo

Figure 12.8 Traffic Noise Assessment - Facade Noise Map - 2026 [PDF 542KB]pdf logo

Figure 13.1 Projected Waste Flows passing through the waste management facilities [PDF 60KB]pdf logo

Figure 14.1 Location of Inner study Area [PDF 791KB]pdf logo

Figure 15.1 Proposed Site layout with Sample Locations and archaeology [ PDF 369KB]pdf logo

Figure 16.1 Site Context Plan - Land Use [PDF 2678KB]pdf logo

Volume 2 - Technical Appendicies 1 to 9

Appendix 1.1 Formal Scoping Request A Main Report [PDF 360KB]pdf logo

Appendix 1.1 Formal Scoping Request Figure 1.1 Site Location Plan [PDF 803KB]pdf logo

Appendix 1.1 Formal Scoping Request Figure 1.2 Application Boundary [PDF 151KB]pdf logo

Appendix 1.1 Formal Scoping Request Figure 1.3 Site Context Plan [PDF 219KB]pdf logo

Appendix 1.1 Formal Scoping Request Figure 2.1 Existing Site Layout [PDF 351KB]pdf logo

Appendix 1.1 Formal Scoping Request Figure 2.3 Aerial Photograph 1 [PDF 162KB]pdf logo

Appendix 1.1 Formal Scoping Request Figure 4.1 Indicative Site Layout [PDF 537KB]pdf logo

Appendix 1.2 Formal Scoping Responses [PDF 4.10KB]pdf logo

Appendix 1.3 Stakeholder Engagement [PDF 1262KB]pdf logo

Appendix 4.1 Outline Construction Programme [PDF 149KB]pdf logo

Appendix 4.2 Clugston Common Policies Environment [PDF 204KB]pdf logo

Appendix 4.3 Example Method Statements etc [PDF 176KB]pdf logo

Appendix 5.1 Alternative Sites Assessment [PDF 1491KB]pdf logo

Appendix 5.1 Alternative Sites Figures [PDF 2899KB]pdf logo

Appendix 5.2 Alternative Technology Appraisal [PDF 591KB]pdf logo

Appendix 5.3 Sustainability Appraisal [PDF 894KB]pdf logo

Appendix 6.1 TA A Main Report [PDF 664KB]pdf logo

Appendix 6.1 TA A X Flysheets [PDF 37KB]pdf logo

Appendix 6.1 TA Appendix A Draft TA Scoping Note [PDF 255KB]pdf logo

Appendix 6.1 TA Appendix B Existing Traffic Flows [PDF 157KB]pdf logo

Appendix 6.1 TA Appendix C Part 1 Committed Development Traffic Flows [PDF 147KB]pdf logo

Appendix 6.1 TA Appendix C Part 2 Committed Development Traffic Flows [PDF 148KB]pdf logo

Appendix 6.1 TA Appendix D Injury Accident Records [PDF 53KB]pdf logo

Appendix 6.1 TA Appendix E Development Traffic Flows [PDF 156KB]pdf logo

Appendix 6.1 TA Appendix F Construction Flows Rev [PDF 144KB]pdf logo

Appendix 6.1 TA Appendix G 2011 Base + Com Dev Flows [PDF 151KB]pdf logo

Appendix 6.1 TA Appendix H 2026 Base + Com Dev Flows [PDF 153KB]pdf logo

Appendix 6.1 TA Appendix I 2011 Total Traffic Flows [PDF 149KB]pdf logo

Appendix 6.1 TA Appendix J 2026 Total Traffic Flows [PDF 153KB]pdf logo

Appendix 6.1 TA Appendix K A617 Traffic Signals LINSIGII Analysis [PDF 1311KB]pdf logo

Appendix 6.1 TA Appendix L Base + Construction Flows [PDF 145KB]pdf logo

Appendix 6.1 TA Figure 1 Site Location Plan [PDF 1144KB]pdf logo

Appendix 6.1 TA Figure 2 Site and Local Transport Network [PDF 464KB]pdf logo

Appendix 6.1 TA Figure 3 Public Transport Services [PDF 50KB]pdf logo

Appendix 7.1 Air Quality Figures[PDF 1953KB]pdf logo

Appendix 7.2 Health Risk Assessment [PDF 2014KB]pdf logo

Appendix 8.1 Viewpoint Assessment [PDF 318KB]pdf logo

Appendix 8.2 Visual Receptors [PDF 318KB]pdf logo

Appendix 9.1 Extended Phase 1 Habitat Survey [PDF 474KB]pdf logo

Appendix 9.1 Figure 9.1 Ecological Constraints Map [PDF 954KB]pdf logo

Appendix 9.1 Figure 9.2 Phase 1 Main Map Main Site [PDF 354KB]pdf logo

Appendix 9.1 Figure 9.3 Phase 1 Map Access Road [PDF 2236KB]pdf logo

Appendix 9.2 Reptile Report Figure 9.4 Location of Reptile Refugia [PDF 244KB]pdf logo

Appendix 9.2 Reptile Report [PDF 255KB]pdf logo

Appendix 9.3 Breeding Bird Surveys Report [PDF 281KB]pdf logo

Appendix 9.3 Figure 9.5 Breeding Bired Survey Transect [PDF 264KB]pdf logo

Appendix 9.3 Figure 9.6 Breeding Bird Survey Visit 1 [PDF 279KB]pdf logo

Appendix 9.3 Figure 9.7 Breeding Bird Survey Visit 2 [PDF 278KB]pdf logo

Appendix 9.3 Figure 9.8 Breeding Bird Survey Visit 3 [PDF 288KB]pdf logo

Appendix 9.3 Figure 9.9 Breeding Bird Survey Visit 4 [PDF 285KB]pdf logo

Appendix 9.4 A Winter Bird Survey [PDF 232KB]pdf logo

Appendix 9.4 Figure 9.10 Wintering Bird Visit 1 [PDF 257KB]pdf logo

Appendix 9.4 Figure 9.11 Wintering Bird Visit 2 [PDF 235KB]pdf logo

Appendix 9.4 Figure 9.12 Wintering Bird Visit 3 [PDF 237KB]pdf logo

Appendix 9.4 Figure 9.13 Wintering Bird Visit 4 [PDF 258KB]pdf logo

Appendix 9.5 Dingy Skipper Report [PDF 244KB]pdf logo

Appendix 9.5 Figure 9.14 Dingy Skipper Survey Transect [PDF 251KB]pdf logo

Appendix 9.6 A Figure 9.1A Designations within 2km [PDF 1383KB]pdf logo

Appendix 9.6 A Figure 9.1B Designations within 10km [PDF 431KB]pdf logo

Appendix 9.6 Appendix A Figure 1 Rainworth Heath SSSI [PDF 788KB]pdf logo

Appendix 9.6 Appendix A Figure 2 Strawberry Hil Heaths SSSI [PDF 838KB]pdf logo

Volume 3 - Technical Appendicies 10 to 17

Appendix 10.1 WQA A Main Report [PDF 256KB]pdf logo

Appendix 10.1 WQA Figure 10.1 Surface Water Features and Sampling locations [PDF 1500KB]pdf logo

Appendix 10.2 A FRA A Report [PDF 321KB]pdf logo

Appendix 10.2 A FRA Figure 1.1 Site Location Plan [PDF 813KB]pdf logo

Appendix 10.2 A FRA Figure 1.2 Application Boundary [PDF 179KB]pdf logo

Appendix 10.2 A FRA Figure 10.1 Surface Water Features and Sampling location [PDF 1468KB]pdf logo

Appendix 10.2 A FRA Figure 10.2 Environment Agency Flood Map [PDF 572KB]pdf logo

Appendix 10.2 A FRA Figure 2.1 Existing Site Layout (Topographical Survey) [PDF 1804KB]pdf logo

Appendix 10.2 A FRA Figure 2.1A Topographical Survey - Stream Sections [PDF 1737KB]pdf logo

Appendix 10.2 A FRA Figure 4.4 Surface Water Management Strategy [PDF 1500KB]pdf logo

Appendix 10.2 A FRA Figure 4.5 Site Plan Showing ERF Layout [PDF 282KB]pdf logo

Appendix 10.2 FRA Appendix A Site Photographs [PDF 491KB]pdf logo

Appendix 10.2 FRA Appendix B Rufford Infiltration Basin Preliminary Design [PDF 53KB]pdf logo

Appendix 10.2 FRA Appendix C Soakaway Test Report [PDF 502KB]pdf logo

Appendix 10.2 FRA Appendix D [PDF 2527KB]pdf logo

Appendix 11.1 A Ground Conditions Phase 1 Report [PDF 423KB]pdf logo

Appendix 11.1 Ground Conditions Phase 1 Report Appendix A EnviroCheck Report [PDF 5076KB]pdf logo

Appendix 11.1 Ground Conditions Phase 1 Report Appendix B Rufford Colliery Plates [PDF 1219KB]pdf logo

Appendix 11.1 Ground Conditions Phase 1 Report Appendix C SI Report Redacted [PDF 15267KB]pdf logo

Appendix 11.1 Ground Conditions Phase 1 Report Appendix D F14276 Factual Report Redacted [PDF 18870KB]pdf logo

Appendix 11.2 Correspondance Redacted [PDF 1338KB]pdf logo

Appendix 12.1 Callibratuion Certificate [PDF 1220KB]pdf logo

Appendix 12.2 Noise Monitoring Results [PDF 222KB]pdf logo

Appendix 12.3 Plant and Equipment List Incorporating Noise Data [PDF 102KB]pdf logo

Appendix 14.1 to 14.12 Data Tables [PDF 790KB]pdf logo

Appendix 14.13 Cluttons Report re House Prices [PDF 3702KB]pdf logo

Appendix 15.1 A Desk Based Archaeological Assessment [PDF 392KB]pdf logo

Appendix 15.1 DBA Figure 1 [PDF 1435KB]pdf logo

Appendix 15.1 DBA Figure 2 [PDF 1152KB]pdf logo

Appendix 15.1 DBA Figure 3 [PDF 409KB]pdf logo

Appendix 15.1 DBA Figure 4 [PDF 366KB]pdf logo

Appendix 15.1 DBA Figure 5 [PDF 913KB]pdf logo

Appendix 15.1 DBA Figure 6 [PDF 727KB]pdf logo

Appendix 15.1 DBA Figure 7 [PDF 559KB]pdf logo

Planning Application Supporting Statement

Appendix A Outline Construction Programme [PDF 149KB]pdf logo

Appendix B Clugston Common Policies Environment [PDF 204KB]pdf logo

Appendix C Example Method Statements etc [PDF 176KB]pdf logo

Appendix D VES General Policy Statements [PDF 3122KB]pdf logo

Appendix E Summary of Results Of Sustainability Appraisal [PDF 229KB]pdf logo

Appendix F Summary of Rufford Public Consultation Feedback Forms [PDF 109KB]pdf logo

Appendix G Design and Access Statement [PDF 1819KB]pdf logo

Appendix I Ecology Method Statements [PDF 130KB]pdf logo

Figures and Drawings - A1 Drawings

010-0-Lvl +100.00 [PDF 502KB]pdf logo

011-0-Level +105.00 [PDF 503KB]pdf logo

012-0-Level +108.50 [PDF 420KB]pdf logo

013-0-Level +117.00 [PDF 250KB]pdf logo

021-0-East & West Facades [PDF 219KB]pdf logo

022-0 ERF South  facade updated 071025 [PDF 124KB]pdf logo

023-0-Internal West Elevations B-C [PDF 239KB]pdf logo

024-0-Internal East Elev D&E [PDF 241KB]pdf logo

025-0 ERF South  facade updated 071025 [PDF 121KB]pdf logo

030-0-Long Section A [PDF 279KB]pdf logo

031-0-Cross Sections 1&2 [PDF 186KB]pdf logo

032-0-Cross Sections 3&5 [PDF 221KB]pdf logo

040-0-Adm-Plans [PDF 265KB]pdf logo

041-0-Adm-Facades [PDF 207KB]pdf logo

042-0-Adm-Sections [PDF 231KB]pdf logo

050-0-Transformer [PDF 169KB]pdf logo

060-0-Circulation Plan [PDF 888KB]pdf logo

Waterman-36810WCLSA950002 [PDF 411KB]pdf logo

Waterman-36810WCLSA950006 [PDF 234KB]pdf logo

Figures and Drawings - A3 Drawings

Figure 1.1 Site Location Plan [PDF 813KB]pdf logo

Figure 1.2 Application Boundary [PDF 179KB]pdf logo

Figure 2.1 Existing Site Layout - Topographical Survey [PDF 1467KB]pdf logo

Figure 2.2 Aerial Photograph 1 [PDF 449KB]pdf logo

Figure 2.3 Aerial Photograph 2 [PDF 459KB]pdf logo

Figure 2.4 Pit Head Area and Associated Development [PDF 2279KB]pdf logo

Figure 2.5 Site Context plan [PDF 748KB]pdf logo

Figure 2.6 Public Rights of Way and Open Access [PDF 800KB]pdf logo

Figure 4.1 ERF Input Output Flow Diagram [PDF 93KB]pdf logo

Figure 4.16 Construction Phase Site Facilities [PDF 2997KB]pdf logo

Figure 4.2 process flow diagram [PDF 1804KB]pdf logo

Figure 4.4 Surface Water Management Strategy [PDF 393KB]pdf logo

Figure 4.9 Computer Generated 3D Image of proposed ERF[PDF 1376KB]

pdf logo

Regulation 19 Response

Return to Rufford Energy Recovery Facility Public Inquiry page.