| Application no: | ES/1144 |
| Site reference: | 3711/W |
| Location: | Land at Former Rufford Colliery, Rainworth |
| Proposal: | Construction and operation of an Energy Recovery Facility through the incineration of waste together with ancillary infrastructure, including a waste bulking/transfer station, administration/visitor centre, landscaping and creation of new internal haul road. |
| Date received: | 30/11/2007 |
| Valid date: | 03/12/2007 |
| Start of Public Consultation: | 03/12/2007 |
| Case Officer: | Mike Hankin |
| Case Officer telephone: | 0115 9774320 |
| Contact e-mail: | development.planning@nottscc.gov.uk |
| Agent's name: | RPS Planning & Development |
| Agent's address: | Conrad House Beaufort Square Chepstow Monmouthshire |
| Applicant's name: | Veolia Environmental Services Nottinghamshire |
| Applicant's address: | Trentside Offices Freeth Street Nottingham |
Planning Submission Documents
Planning Application Submission – contained on cd rom. This is split into a Non-technical summary, a planning supporting statement, the Environmental Impact Assessment and the supporting technical appendixes.
ATTENTION:
Some files particularly those containing complex drawings have been reduced in file size and print quality to assist in download speeds. The original full size documents are available in the planning application CD-ROM. Copies are available upon request by contacting the Development Control Team.
ES Non-Technical Summary
Figure 1.1 Site Location Plan [PDF 815KB]
Figure 1.2 Application Boundary [PDF 181KB]
Figure 2.5 Site Context plan [PDF 750KB]
Figure 4.1 ERF Input Output Flow Diagram [PDF 93KB]
Figure 4.2 process flow diagram [PDF 3010KB]
Figure 4.3 Landscape Masterplan [PDF 3080KB]
Figure 4.9 Computer Generated 3D Image of proposed ERF [PDF 395KB]
Figure 9.1A Designations within 2km [PDF 1300KB]
Non-Technical Summary text [PDF 250KB]
Volume 1 - Environmental Statement
Chapter 1 Introduction [PDF 371KB]
Chapter 2 The Site and its Setting {PDF 163KB]
Chapter 3 Planning History and Policy [PDF 751KB]
Chapter 4 Development Proposals [PDF 720KB]
Chapter 5 Need and Alternatives [PDF 714KB]
Chapter 6 Traffic and Transport [PDF 388KB]
Chapter 7 Air Quality [PDF 961KB]
Chapter 8 Landscape and Visual [PDF 923KB]
Chapter 10 Hydrology and Flood [PDF 352KB]
Chapter 11 Grounf Conditions and Hydrogeology [PDF 388KB]
Chapter 14 Socio Economic Impacts [PDF 334KB]
Chapter 15 Archaeology and Cultural Heritage [PDF 310KB]
Chapter 16 Land Use [PDF 268KB]
Chapter 17 Summary [PDF 661KB]
Volume 1 - Environmental Statement - Figures
Figure 1.1 Site Location Plan [PDF 812KB]
Figure 1.2 Application Boundary [PDF 179KB]
Figure 2.1 Existing Site Layout - Topographical Survey [PDF 1467KB]
Figure 2.2 Aerial Photograph 1 [PDF 449KB]
Figure 2.3 Aerial Photograph 2 [PDF 459KB]
Figure 2.4 Pit Head Area and Associated Development [PDF 2279KB]
Figure 2.5 Site Context plan [PDF 748KB]
Figure 2.6 Public Rights of Way and Open Access [PDF 800KB]
Figure 4.1 ERF Input Output Flow Diagram [PDF 93KB]
Figure 4.2 process flow diagram [PDF 2997KB]
Figure 4.3 Landscape Masterplan [PDF 418KB]
Figure 4.4 Surface Water Management Strategy [PDF 1804KB]
Figure 4.5 Site Plan Showing ERF Layout [PDF 1737KB]
Figure 4.6 West and East Facades [PDF 340KB]
Figure 4.7 North and South Facades [PDF 315KB]
Figure 4.8 Long Section A-A [PDF 626KB]
Figure 4.9 Computer Generated 3D Image of proposed ERF [PDF 393KB]
Figure 4.10 Administration Building Elevations [PDF 192KB]
Figure 4.11 Transformer Building [PDF 191KB]
Figure 4.12 Vehicle Circulation Plan [PDF 474KB]
Figure 4.13 Pedestrian Visitors Route [PDF 424KB]
Figure 4.14 General Arrangement of New Internal Colliery Road [PDF 190KB]
Figure 4.15 Cross Section of New Internal Colliery Road [PDF 133KB]
Figure 4.16 Construction Phase Site Facilities [PDF 1376KB]
Figure 5.1 Forecast Municipal Solid Waste Generation [PDF 719KB]
Figure 5.2 Forecast Recycling of Municipal Waste Arisings [PDF 764KB]
Figure 5.3 Management of Residual Waste [PDF 109KB]
Figure 5.4 Performance against LDA with ERF [PDF 211KB]
Figure 5.5 Performance against LDA with Do Nothing [PDF 129KB]
Figure 5.6 Design Evolution [PDF 526KB]
Figure 6.1 Site Location Plan [PDF 1144KB]
Figure 6.2 Site and Local Transport Network [PDF 465KB]
Figure 7.1 ERF Site and Nearest Sensitive Receptors [PDF 1505KB]
Figure 7.2 Contour Plot Predicted annual n02 [PDF 779KB]
Figure 7.3 Contour Plot Predicted annual pm10 [PDF 823KB]
Figure 8.1 Existing Site Context [PDF 577KB]
Figure 8.2 Topographical Context [PDF 963KB]
Figure 8.3 Landscape Policy Context [PDF 631KB]
Figure 8.4 Landscape Character Context [PDF 678KB]
Figure 8.5 75m Chimney ZVI [PDF 736KB]
Figure 8.6 40m Roof ZVI [PDF 790KB]
Figure 8.7 Viewpoint Locations [PDF 592KB]
Figure 8.8 Viewpoint 1 Assessment [PDF 361KB]
Figure 8.8b Viewpoint 1 Photomontage [PDF 1713KB]
Figure 8.9 Viewpoint 2 Assessment [PDF 2594KB]
Figure 8.9b Viewpoint 2 Photomontage [PDF 754KB]
Figure 8.10 Viewpoint 3 [PDF 2832KB]
Figure 8.11 Viewpoint 4 [PDF 2664KB]
Figure 8.11b Viewpoint 4 Photomontage [PDF 3005KB]
Figure 8.12 Viewpoint 5 [PDF 3133KB]
Figure 8.13 Viewpoint 6 [PDF 2487KB]
Figure 8.13b Viewpoint 6 Photomontage [PDF 2884KB]
Figure 8.14 Viewpoint 7 [PDF 2564KB]
Figure 8.15 Viewpoint 8 [PDF 869KB]
Figure 8.16 Viewpoint 9 [PDF 1386KB]
Figure 8.17 Viewpoint 10 [PDF 3150KB]
Figure 8.17b Viewpoint 10 Photomontage [PDF 3390KB]
Figure 8.18 Viewpoint 11 [PDF 865KB]
Figure 8.19 Viewpoint 12 [PDF 1133KB]
Figure 8.20 Viewpoint 13 [PDF 447KB]
Figure 9.1 Ecological Constraints Map [PDF 954KB]
Figure 9.14 Dingy Skipper Survey Transect [PDF 1383KB]
Figure 9.1A Designations within 2km [PDF 431KB]
Figure 9.1B Designations within 10km [PDF 354KB]
Figure 9.2 Phase 1 Main Map Main Site [PDF 2236KB]
Figure 9.3 Phase 1 Map Access Road [PDF 254KB]
Figure 9.4 Location of Reptile Refugia [PDF 264KB]
Figure 9.5 Breeding Bired Survey Transect [PDF 251KB]
Figure 10.1 Surface Water Features [PDF 1467KB]
Figure 10.2 Environment Agency Flood Map [PDF 449KB]
Figure 11.1 Proposed Site Layout and Sample locations [PDF 337KB]
Figure 11.2 Solid and Drift Geology [PDF 1220KB]
Figure 11.3 potential Groundwater receptor plan-high [PDF 919KB]
Figure 12.1 Noise Monitoring Locations [PDF 652KB]
Figure 12.2 - Grid Noise - All Sources (Internal, External, Glass Bays & HGV) [PDF 499KB]
Figure 12.4 Traffic Noise Assessment - Grid Noise Map - 2011 Base + Dvpt Flows [PDF 589KB]
Figure 12.6 Traffic Noise Assessment - Grid Noise Map - 2026 Base + Development Flows [PDF 596KB]
Figure 12.8 Traffic Noise Assessment - Facade Noise Map - 2026 [PDF 542KB]
Figure 13.1 Projected Waste Flows passing through the waste management facilities [PDF 60KB]
Figure 14.1 Location of Inner study Area [PDF 791KB]
Figure 15.1 Proposed Site layout with Sample Locations and archaeology [ PDF 369KB]
Figure 16.1 Site Context Plan - Land Use [PDF 2678KB]
Volume 2 - Technical Appendicies 1 to 9
Appendix 1.1 Formal Scoping Request A Main Report [PDF 360KB]
Appendix 1.1 Formal Scoping Request Figure 1.1 Site Location Plan [PDF 803KB]
Appendix 1.1 Formal Scoping Request Figure 1.2 Application Boundary [PDF 151KB]
Appendix 1.1 Formal Scoping Request Figure 1.3 Site Context Plan [PDF 219KB]
Appendix 1.1 Formal Scoping Request Figure 2.1 Existing Site Layout [PDF 351KB]
Appendix 1.1 Formal Scoping Request Figure 2.3 Aerial Photograph 1 [PDF 162KB]
Appendix 1.1 Formal Scoping Request Figure 4.1 Indicative Site Layout [PDF 537KB]
Appendix 1.2 Formal Scoping Responses [PDF 4.10KB]
Appendix 1.3 Stakeholder Engagement [PDF 1262KB]
Appendix 4.1 Outline Construction Programme [PDF 149KB]
Appendix 4.2 Clugston Common Policies Environment [PDF 204KB]
Appendix 4.3 Example Method Statements etc [PDF 176KB]
Appendix 5.1 Alternative Sites Assessment [PDF 1491KB]
Appendix 5.1 Alternative Sites Figures [PDF 2899KB]
Appendix 5.2 Alternative Technology Appraisal [PDF 591KB]
Appendix 5.3 Sustainability Appraisal [PDF 894KB]
Appendix 6.1 TA A Main Report [PDF 664KB]
Appendix 6.1 TA A X Flysheets [PDF 37KB]
Appendix 6.1 TA Appendix A Draft TA Scoping Note [PDF 255KB]
Appendix 6.1 TA Appendix B Existing Traffic Flows [PDF 157KB]
Appendix 6.1 TA Appendix C Part 1 Committed Development Traffic Flows [PDF 147KB]
Appendix 6.1 TA Appendix C Part 2 Committed Development Traffic Flows [PDF 148KB]
Appendix 6.1 TA Appendix D Injury Accident Records [PDF 53KB]
Appendix 6.1 TA Appendix E Development Traffic Flows [PDF 156KB]
Appendix 6.1 TA Appendix F Construction Flows Rev [PDF 144KB]
Appendix 6.1 TA Appendix G 2011 Base + Com Dev Flows [PDF 151KB]
Appendix 6.1 TA Appendix H 2026 Base + Com Dev Flows [PDF 153KB]
Appendix 6.1 TA Appendix I 2011 Total Traffic Flows [PDF 149KB]
Appendix 6.1 TA Appendix J 2026 Total Traffic Flows [PDF 153KB]
Appendix 6.1 TA Appendix K A617 Traffic Signals LINSIGII Analysis [PDF 1311KB]
Appendix 6.1 TA Appendix L Base + Construction Flows [PDF 145KB]
Appendix 6.1 TA Figure 1 Site Location Plan [PDF 1144KB]
Appendix 6.1 TA Figure 2 Site and Local Transport Network [PDF 464KB]
Appendix 6.1 TA Figure 3 Public Transport Services [PDF 50KB]
Appendix 7.1 Air Quality Figures[PDF 1953KB]
Appendix 7.2 Health Risk Assessment [PDF 2014KB]
Appendix 8.1 Viewpoint Assessment [PDF 318KB]
Appendix 8.2 Visual Receptors [PDF 318KB]
Appendix 9.1 Extended Phase 1 Habitat Survey [PDF 474KB]
Appendix 9.1 Figure 9.1 Ecological Constraints Map [PDF 954KB]
Appendix 9.1 Figure 9.2 Phase 1 Main Map Main Site [PDF 354KB]
Appendix 9.1 Figure 9.3 Phase 1 Map Access Road [PDF 2236KB]
Appendix 9.2 Reptile Report Figure 9.4 Location of Reptile Refugia [PDF 244KB]
Appendix 9.2 Reptile Report [PDF 255KB]
Appendix 9.3 Breeding Bird Surveys Report [PDF 281KB]
Appendix 9.3 Figure 9.5 Breeding Bired Survey Transect [PDF 264KB]
Appendix 9.3 Figure 9.6 Breeding Bird Survey Visit 1 [PDF 279KB]
Appendix 9.3 Figure 9.7 Breeding Bird Survey Visit 2 [PDF 278KB]
Appendix 9.3 Figure 9.8 Breeding Bird Survey Visit 3 [PDF 288KB]
Appendix 9.3 Figure 9.9 Breeding Bird Survey Visit 4 [PDF 285KB]
Appendix 9.4 A Winter Bird Survey [PDF 232KB]
Appendix 9.4 Figure 9.10 Wintering Bird Visit 1 [PDF 257KB]
Appendix 9.4 Figure 9.11 Wintering Bird Visit 2 [PDF 235KB]
Appendix 9.4 Figure 9.12 Wintering Bird Visit 3 [PDF 237KB]
Appendix 9.4 Figure 9.13 Wintering Bird Visit 4 [PDF 258KB]
Appendix 9.5 Dingy Skipper Report [PDF 244KB]
Appendix 9.5 Figure 9.14 Dingy Skipper Survey Transect [PDF 251KB]
Appendix 9.6 A Figure 9.1A Designations within 2km [PDF 1383KB]
Appendix 9.6 A Figure 9.1B Designations within 10km [PDF 431KB]
Appendix 9.6 Appendix A Figure 1 Rainworth Heath SSSI [PDF 788KB]
Appendix 9.6 Appendix A Figure 2 Strawberry Hil Heaths SSSI [PDF 838KB]
Volume 3 - Technical Appendicies 10 to 17
Appendix 10.1 WQA A Main Report [PDF 256KB]
Appendix 10.1 WQA Figure 10.1 Surface Water Features and Sampling locations [PDF 1500KB]
Appendix 10.2 A FRA A Report [PDF 321KB]
Appendix 10.2 A FRA Figure 1.1 Site Location Plan [PDF 813KB]
Appendix 10.2 A FRA Figure 1.2 Application Boundary [PDF 179KB]
Appendix 10.2 A FRA Figure 10.1 Surface Water Features and Sampling location [PDF 1468KB]
Appendix 10.2 A FRA Figure 10.2 Environment Agency Flood Map [PDF 572KB]
Appendix 10.2 A FRA Figure 2.1 Existing Site Layout (Topographical Survey) [PDF 1804KB]
Appendix 10.2 A FRA Figure 2.1A Topographical Survey - Stream Sections [PDF 1737KB]
Appendix 10.2 A FRA Figure 4.4 Surface Water Management Strategy [PDF 1500KB]
Appendix 10.2 A FRA Figure 4.5 Site Plan Showing ERF Layout [PDF 282KB]
Appendix 10.2 FRA Appendix A Site Photographs [PDF 491KB]
Appendix 10.2 FRA Appendix B Rufford Infiltration Basin Preliminary Design [PDF 53KB]
Appendix 10.2 FRA Appendix C Soakaway Test Report [PDF 502KB]
Appendix 10.2 FRA Appendix D [PDF 2527KB]
Appendix 11.1 A Ground Conditions Phase 1 Report [PDF 423KB]
Appendix 11.1 Ground Conditions Phase 1 Report Appendix A EnviroCheck Report [PDF 5076KB]
Appendix 11.1 Ground Conditions Phase 1 Report Appendix B Rufford Colliery Plates [PDF 1219KB]
Appendix 11.1 Ground Conditions Phase 1 Report Appendix C SI Report Redacted [PDF 15267KB]
Appendix 11.2 Correspondance Redacted [PDF 1338KB]
Appendix 12.1 Callibratuion Certificate [PDF 1220KB]
Appendix 12.2 Noise Monitoring Results [PDF 222KB]
Appendix 12.3 Plant and Equipment List Incorporating Noise Data [PDF 102KB]
Appendix 14.1 to 14.12 Data Tables [PDF 790KB]
Appendix 14.13 Cluttons Report re House Prices [PDF 3702KB]
Appendix 15.1 A Desk Based Archaeological Assessment [PDF 392KB]
Appendix 15.1 DBA Figure 1 [PDF 1435KB]
Appendix 15.1 DBA Figure 2 [PDF 1152KB]
Appendix 15.1 DBA Figure 3 [PDF 409KB]
Appendix 15.1 DBA Figure 4 [PDF 366KB]
Appendix 15.1 DBA Figure 5 [PDF 913KB]
Appendix 15.1 DBA Figure 6 [PDF 727KB]
Appendix 15.1 DBA Figure 7 [PDF 559KB]
Planning Application Supporting Statement
Appendix A Outline Construction Programme [PDF 149KB]
Appendix B Clugston Common Policies Environment [PDF 204KB]
Appendix C Example Method Statements etc [PDF 176KB]
Appendix D VES General Policy Statements [PDF 3122KB]
Appendix E Summary of Results Of Sustainability Appraisal [PDF 229KB]
Appendix F Summary of Rufford Public Consultation Feedback Forms [PDF 109KB]
Appendix G Design and Access Statement [PDF 1819KB]
Appendix I Ecology Method Statements [PDF 130KB]
Figures and Drawings - A1 Drawings
011-0-Level +105.00 [PDF 503KB]
012-0-Level +108.50 [PDF 420KB]
013-0-Level +117.00 [PDF 250KB]
021-0-East & West Facades [PDF 219KB]
022-0 ERF South facade updated 071025 [PDF 124KB]
023-0-Internal West Elevations B-C [PDF 239KB]
024-0-Internal East Elev D&E [PDF 241KB]
025-0 ERF South facade updated 071025 [PDF 121KB]
030-0-Long Section A [PDF 279KB]
031-0-Cross Sections 1&2 [PDF 186KB]
032-0-Cross Sections 3&5 [PDF 221KB]
042-0-Adm-Sections [PDF 231KB]
060-0-Circulation Plan [PDF 888KB]
Waterman-36810WCLSA950002 [PDF 411KB]
Waterman-36810WCLSA950006 [PDF 234KB]
Figures and Drawings - A3 Drawings
Figure 1.1 Site Location Plan [PDF 813KB]
Figure 1.2 Application Boundary [PDF 179KB]
Figure 2.1 Existing Site Layout - Topographical Survey [PDF 1467KB]
Figure 2.2 Aerial Photograph 1 [PDF 449KB]
Figure 2.3 Aerial Photograph 2 [PDF 459KB]
Figure 2.4 Pit Head Area and Associated Development [PDF 2279KB]
Figure 2.5 Site Context plan [PDF 748KB]
Figure 2.6 Public Rights of Way and Open Access [PDF 800KB]
Figure 4.1 ERF Input Output Flow Diagram [PDF 93KB]
Figure 4.16 Construction Phase Site Facilities [PDF 2997KB]
Figure 4.2 process flow diagram [PDF 1804KB]
Figure 4.4 Surface Water Management Strategy [PDF 393KB]
Figure 4.9 Computer Generated 3D Image of proposed ERF[PDF 1376KB]
Regulation 19 Response
- 1st Regulation 19 response – available on NCC website
- 2nd Regulation 19 response – available on NCC Website
Return to Rufford Energy Recovery Facility Public Inquiry page.